Afridev Hand Pump Spares Required for Rehabilitation

Hello Everyone,

Today, we will talk about Afridev hand pump spare parts which are required during the basic rehabilitation process. There are two type of rehabilitations i.e one is minor and other is major.

if you look after your borehole and keep inspecting from area mechanic after every 6 months then we call it Minor Rehabilitation. Another one is major when communities or the owner of the borehole does not bother and pump gets damaged badly then you need to change major spare parts of borehole hand pump that is called Major Rehabilitation.


 Following are the parts to change during Minor Rehabilitation:

1. Cup Seal or U Seal
2. Bobbin
3. Rod Centralizer
4. Bush Bearing

Following are the parts to change during Major Rehabilitation:

1.   Cup Seal or U Seal
2.   Bobbin
3.   Rod Centralizer
4.   Bush Bearing
5.   PipeCentralizer
6.   Fulcrum Pin
7.   Head Only
8.   Stainless Steel Rod
9.   Pipe
10. Flapper
11. Nut and Bolt
12. Handle Assy


There is a big difference in between minor and major rehabilitation budget, therefore, we recommend inspection should get it done by area mechanic in every 6 months. All above-mentioned spares are depicted in above picture of company ESS ESS Malawi who keeps all spares in their local branches which are near-by your area in the districts.

if you have any question then please free to ask or discuss with us to solve water issues as this is the main motive of this draft. your opinions are welcome here. Maybe we can make difference with our joint efforts.